CASE STUDY  ROAD & ROAD CONSTRUCTION EQUIPMENT






























           Easter Peripheral Expressway





           Delivered at Express Speed...Powered by 87 machines of Schwing Stetter India
           “2 x Stetter M2.5 concrete batching plant worked nonstop to produce a total volume of 6750 m  of Pavement
                                                                                                    3
           Quality Concrete in a single working day”
           This 135 Km, India‘s first green, smart  Concreting at EPE:           project completion period compared to the
           Eastern Peripheral Expressway (EPE)   In order to stick to the deadlines issued  targeted 30 months’ period.
           aims to decongest Delhi thereby reducing  by the Government of India, the project     e massive initiative has 8 interchanges,
           pollution. It will bypass Delhi on the   execution team of Ashoka Buildcon,   46 small bridges, 151 pedestrian trails, 141
           eastern  side  and  covers  Haryana,  Delhi   Gayatri projects, Jaiprakash  associates,   culvert, 4  yovers, 71 vehicle underpasses,
           and Uttar Pradesh.   e expressway will   Oriental structural engineers and Sadbhav  and 8 RoB’s—a  total  of 400  structures,
           provide connectivity between Delhi and   engineering chose Schwing Stetter India   out of which two major bridges are on
           the towns of Ghaziabad, Faridabad, Greater   equipment as it’s known for its meticulous  the rivers Yamuna and Hindon were built
           Noida and Sonipat.   e project involves  quality, e  ciency, longevity and remarkable   with concrete using Schwing Stetter India
           construction of a six-lane expressway with   customer feedback.       equipment.
           access control from Faridabad to Sonipat.   A crucial role has been played by the  It took a massive 5 lakh tonnes of cement,
             e expressway will have two sections, the   concreting equipment. A total of eighty   1 lakh tonne of steel and a total volume of
           56 km-long Faridabad - Ghaziabad section  three concreting equipment; nineteen   concrete that was poured and produced
                                                                                                   3
           and the 49 km-long Ghaziabad – Sonipat   numbers of Stetter batching plants along   is around 20 Lakh m  for this project.
           section.   e completed expressway will help   with five numbers of Stetter chilling  Schwing Stetter India equipment in use at
           relieve tra  c congestion in the Faridabad –  plant, forty seven numbers of Stetter  this project are listed below.
           Ghaziabad stretch.                 transit mixers of various
             is project is being constructed by Ashoka   capacities ranging from 6   Material   Model  Quantity
                                                      3
                                               3
           Buildcon, Gayatri projects, Jaiprakash   m  to 10 m , ten numbers        H6N, H4N, H3N          4
           associates, Oriental structural engineers and   of Schwing stationary  Batching Plant  M1, M1T, M1.25, M2.5  9
           Sadbhav engineering.  e project execution   concrete pumps and six      CP 30, CP 45           6
           was divided into six packages - 21-km   numbers of Schwing truck         BP 1800, SP 1200       2
           stretch in Sonepat-Baghpat, 24.5 km stretch   mounted concrete boom  Concrete Pump
           in Baghpat-Ghaziabad, 24.5-km stretch in   pumps  were  at  action  to   BP 350 D               8
           Ghaziabad-GB Nagar, 22-km stretch in   batch mix, transport, pour  Concrete Boom Pump  S34X, S36X, KVM 32  6
           GB Nagar, 21-km stretch in GN Nagar-  and place concrete in the  Concrete Transit Mixer  (of various capacities)  47
           Faridabad and 22-km stretch in Faridabad-  Expressway with a record   Chilling Plant  90 TR, 150 TR  5
           Palwal.                            breaking in 18 months