         INFRASTRUCTURE  The road transport and highways sector has the maximum number   their original schedules and 272 projects have reported additional
              ROAD TRANSPORT AND HIGHWAYS SECTOR HAS MAXIMUM
                        NUMBER OF DELAYED PROJECTS
                                                               delays vis-a-vis their date of completion reported in the previous
                                                               month. Of these 272 projects, 59 are mega projects costing 1,000
           of delayed projects at 460, followed by railways at 117 and the
                                                               crore and above.
                                                               About the road transport and highways sector, the report stated
           petroleum industry at 90, showed a government report. In the road
                                                               that the total original cost of implementation of 749 projects when
           transport and highways sector, 460 out of 749 projects are delayed.
                                                               sanctioned was of the order of `4,09,053.84 crore, but this was
           In railways, out of 173 projects, 117 are delayed, while in the
           petroleum sector, 90 out of 152 projects are running behind
           schedule, as per the latest flash report on infrastructure projects
                                                               overrun of 4.5 per cent. The expenditure incurred on these projects
                                                               till January 2023 was `2,34,935.32 crore, which was 55 per cent of
           for January 2023. The Infrastructure and Project Monitoring Division   subsequently anticipated at `4,27,518.41 crore, implying a cost
           (IPMD) is mandated to monitor central sector infrastructure projects   the anticipated cost of the projects.
           costing `150 crore and above based on the information provided   Similarly, in railways, the total original cost of implementation of 173
           on the Online Computerised Monitoring System (OCMS) by the   projects when sanctioned was of the order of `3,72,761.45 crore
           project implementing agencies. The IPMD comes under the   but this was subsequently anticipated to rise to `6,26,632.52 crore,
           Ministry of Statistics and Programme Implementation.  implying a cost overrun of 68.1 per cent. The expenditure incurred
           The report showed that the Muneerabad-Mahaboobnagar rail   on these projects till January 2023 was `3,72,172.64 crore, which
           project is the most delayed project. It is delayed by 276 months.  was 59.4 per cent of the anticipated cost of the projects.
           The second-most delayed project is the Udhampur-Srinagar-  About the petroleum sector, it said the total original cost of
           Baramulla rail project, which is delayed by 247 months. The   implementation of 152 projects when sanctioned was of the order
           third-most delayed project, Belapur-Seawood-Urban Electrified   of `3,78,090.07 crore, but this was subsequently anticipated to
           Double Line, is running 228 months behind schedule. The flash   increase to `3,96,608.48 crore, implying a cost overrun of 4.9 per
           report for January 2023 contains information on the status of the   cent. The expenditure incurred on these projects till January 2023
           1,454 central sector infrastructure projects costing Rs 150 crore   was `1,49,364.38 crore, which was 37.7 per cent of the anticipated
           and above. As many as 871 projects are delayed with respect to   cost of the projects.

             DELHI-DEHRADUN EXPRESSWAY TO BE COMPLETE BY DEC END  visited the Ashram to take part in a Ganga Aarti along with family
           The construction work of the Delhi-Dehradun Expressway will   said the all-weather road project will make year-round Char Dham
           be complete by the end of December this year, reducing the   Yatra possible. “Char Dham Yatra goes on for six months at present.
           journey time between the two cities to two hours, Minister of Road   But, once the all-weather road project is complete, devotees can
           Transport and Highways Nitin Gadkari said. “Work on the Delhi-  visit the Himalayan temples throughout the year,” he said. Work
           Dehradun Expressway project will be over by December end and   on the ropeway project in Kedarnath whose foundation stone was
           from January 1 next year people will be travelling from Dehradun   laid by Prime Minister Narendra Modi in October, 2022 has also
           to Delhi in just two hours,” Gadkari said during a visit to Parmarth   begun, he said. The 12.97-km ropeway, the longest in the world at
           Niketan Ashram in Rishikesh recently. A journey from Dehradun to   an altitude of 11,500 feet, will go from Sonprayag to the Himalayan
           Delhi at present takes around six hours. The union minister who   temple.

           POWER GRID WINS PROJECT TO BUILD TRANSMISSION SYSTEM IN   through Tariff Based Competitive Bidding. This will help strengthen
                               RAJASTHAN                       the transmission infrastructure and enable the evacuation of power
           Power Grid Corporation of India Limited has successfully won   generated from the solar energy zones in Rajasthan. It’s a significant
           the  bid  to  establish an  inter-state  transmission  system  for  the   step towards achieving India’s renewable energy targets and
           ‘Transmission System Strengthening Scheme for Evacuation of   promoting sustainable development. The LoI pertains to a project
           Power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-  which involves setting up a 765kV D/c Transmission Line in the State
           II Part-E’ on a Build, Own, Operate, and Maintain (BOOM) basis   of Rajasthan, along with relevant Line Bays.


             BENGALURU-MYSURU EXPRESSWAY IMPORTANT PROJECT, WILL
                     CONTRIBUTE TO KARNATAKA’S GROWTH
           Prime Minister Narendra Modi recently said the Bengaluru-
           Mysuru Expressway was an important connectivity project that will
           contribute to Karnataka’s growth trajectory. The expressway is set
           for inauguration soon. Modi tagged a tweet by Minister of Road
           Transport and Highways Nitin Gadkari who said the construction of
           the Bengaluru-Mysuru Expressway, which encompasses a portion
           of NH-275, entails the development of four rail overbridges, nine
           significant bridges, 40 minor bridges, and 89 underpasses and
           overpasses. “An important connectivity project which will contribute
           to Karnataka’s growth trajectory,” Modi said of the project.