COVER STORY
CASE STUDY
With the aid of the SCS Climbing System for non-tied wall formwork, it was possible to transfer the loads resulting from the fresh concrete
pressure of the second concreting section through climbing ties and into the previous concreting section via the brackets
a multi-purpose manner. For example, it was possible to form the To form the slabs, TABLE MODULE VT Slab Table was used in
columns in a single operation and without the use of any special- combination with VT 20K Formwork Girders, which stand out due
purpose components. Opting for the LIWA system instead of a to their high coast-effectiveness. The large-scale formwork areas
conventional formwork system resulted in valuable time savings of the slab tables were moved quickly and easily by crane and
and a significant reduction in personnel costs. movable trolley. The slab tables were pre-assembled at site,
meaning they were ready for use in no time at all, thus contributing
Modular scaffold system as a height-adaptable table support to the smooth execution of the time-critical construction schedule.
The construction site team came up against another challenge
when it came to constructing the 750-mm-thick slab area and the Comprehensive on-site support from PERI
1,200-mm-thick roof floor covering 24 m x 32 m single pour plan PERI has delivered around 480 tonnes of formwork and scaffolding
area. The solution came in the form of the height-adaptable table material to the client’s construction site. The planning and
support PERI UP Flex Shoring Tower Plus. With the aid of standards construction engineers from PERI have also been on hand to
and horizontal ledgers of the modular scaffold PERI UP Flex and a support and train the construction site team throughout the entire
few additional components, it was possible to erect shoring that process in an effort to ensure that the major construction project is
was ideally suited to slab tables. It was also possible to adjust the completed within the scheduled construction period of 14 months.
positions of the standards so that they were perfectly equipped The Bandra Kurla Complex is scheduled for completion in 2020.
to deal with the loads to be transferred, with each standard being
able to absorb a maximum load of 40 kN. For more details visit: www.peri.in
On account of the subterranean position up against the ground earth, it was not possible to use end-to-end formwork ties when
concreting the retaining walls. For this reason, a single-sided formwork solution was required.