Page 62 - January_2023
P. 62

INFRASTRUCTURE   Work on the railways’ ambitious bullet train project between   management and operating capabilities, together with that
            TICKER TAPE
            MORE THAN 98 PC LAND ACQUIRED FOR BULLET TRAIN
               PROJECT IN MAHARASHTRA: RAILWAY MINISTRY
                                                               of L&T IDPL, will help scale up this platform,” Sreekumar Chatra,
                                                               Managing Director, Infrastructure Yield Strategy said.
                                                                “Asset monetization and recycling capital holds the key to value
           Mumbai and Ahmedabad has gained momentum, with the
           ministry claiming that more than 98 per cent of the land has
                                                               creation and development in Infrastructure. We will continue to
                                                               provide solutions to construction companies and developers
           been acquired for the project in Maharashtra. Piers have been
                                                               to recycle capital to fund their growth. On completion of this
           erected for a distance of more than 118 kilometres, girders are
           being launched and the work on the construction of bullet train
                                                               portfolio of 26 assets across  13 states, making us a leading
           stations has also started, the railway ministry said. With the change
           of government in Maharashtra, the pain points in the project in   acquisition, there will be a high-quality diversified infrastructure
                                                               infrastructure investor in India,” Subahoo Chordia, Head -
           terms of forest clearances and land acquisition seem to have   Infrastructure Funds, Edelweiss Alternatives said.
           been overcome.
           In a series of tweets, the ministry claimed that while 98.22 per cent   DELAYED HIGHWAY PROJECTS CAUSE MASSIVE PILE-UP
           land has been acquired in Maharashtra, in Gujarat, 98.87 per cent   OF CLAIMS, GOVT SAYS LARGE CASES ARE FROM UPA
           land has been acquired and in Dadra and Nagar Haveli, 100 per              DAYS
           cent of the land has been acquired for the project.  There is a massive pile up of claims from highway developers,
           The physical progress till November 23 was 24.1 per cent, the   which in some cases is as high as 13 times the original project cost.
           ministry said, adding that while almost 30 per cent of the work   While the 17 cases mentioned in a Parliamentary committee
           has been completed in Gujarat, in Maharashtra, around 13 per   report submitted on Thursday have pending claims of `62,193
           cent has so far been achieved.                      crore, the total claims of private developers now top `1 lakh
           The Mumbai-Ahmedabad bullet train project is of 508 km and   crore, sources told TOI. Even NHAI, the agency responsible for
           most of it is in Gujarat. In Maharashtra, the National High Speed   construction of highways, does not seem to be lagging behind. It
           Rail Corporation Limited (NHSRCL), the implementing agency of   has filed counter-claims of nearly `50,000 crore..
           the project, has to develop the Bandra-Kurla Complex and the   The numbers come at a time when the government is seeking
           network in Thane, Virar and Boisar.                 to reduce litigation and settle disputes in the highway sector as
           Officials said almost all the civil work have been allotted in Gujarat,   several road projects had been delayed due to disputes between
           along with construction of piers (pillars) and all small and big   developers and NHAI. In its defence, the government is arguing
           bridges across rivers. The work of placing girders on the piers has   that projects involving large claims pertain to the UPA days when
           also started.                                       those were bid out on public private partnership (PPP) mode.
           The contract for the construction of a bullet train station at the   According to the report, the private players have raised the claims
           Bandra-Kurla Complex and the one for the construction of an   on ground of delay in declaration of appointed date, delay in
           underground tunnel have also been allotted. Pier and girder works   obtaining environment clearance, prolongation of project due
           will soon be visible in Maharashtra like in Gujarat, officials said.  to various reasons, termination payment, loss of toll revenue,
           In Gujarat, the construction of bullet train stations has started in   delay in commencement of toll operation, loss of productivity of
           Anand, Surat, Vadodara, Bharuch, Vilimora, Vapi and Navsari   machinery and loss of revenue to the concessionaires envisaged
           districts.                                          in the financial model before accepting the project.
                                                               For example, the concessionaire of Madurai-Tuticorin highway
              EDELWEISS ACQUIRES L&T-CPPIB INFRASTRUCTURE      widening project has raised a claim of `8,199 crore, while the
                         PROJECT FOR `6,000 CR                 project cost was barely  `629 crore, citing multiple reasons.
           India’s largest construction company Larsen & Toubro and   Similarly, the concessionaire of four-laning of Mulbagal-Andhra
           Canadian  pension  fund  manager  Canada  Pension  Plan   Pradesh/Karnataka border has raised `2,133 crore claim against
           Investment Board have agreed to transfer their 100% shareholding   the original cost of `154 crore. Only in the Gurgaon-Jaipur project,
           in L&T Infrastructure Development Projects and its subsidiaries   the NHAI has raised a bigger counter claim of  `14,952 crore
           to Edelweiss Alternative Asset Advisors’s Infrastructure Yield Plus   against the contractor, while the private player has made claims
           Strategy fund for an enterprise value of `6,000 crore.  of `4,287 crore.
           L&T Infrastructure Development Projects is a joint venture between   To deal with the disputes and fast-track the alternate resolution of
           L&T and Canada Pension Plan Investment Board holding 51% and   such cases, the government has created two special arbitration
           49% stake respectively. L&T Infrastructure Development Projects   mechanisms, which have made some success. Sources said
           portfolio comprises eight roads and one power transmission asset   in recent months, NHAI has been able to fast-track the one-
           in India, spanning 4,900 lane-kms and 960 ckms respectively.   time settlement of claims by the Conciliation Committees of
           With this acquisition, Edelweiss Alternatives will have a diversified   Independent  Experts.  Officials  said there have  been  several
           portfolio of 26 infrastructure assets comprising over 5,100 lane-kms   cases where private players have raised claims and were going
           of roads, 1,800 ckms of power transmission assets and ~813 MWp   for litigations as well.
           of renewables, Edelweiss Financial said in an exchange filing.  Taking note of this, the Parliamentary panel has asked the highways
            “These assets have a proven track record of operations, are   ministry to apprise it of the steps being taken “to penalise road
           geographically dispersed and have long residual life, which is   contractors, who habitually take projects to litigation without solid
           consistent with our investment strategy. We believe our asset   basis”, causing undue delays in completion of road projects.


        62   CONSTRUCTION OPPORTUNITIES|JANUARY 2023
   57   58   59   60   61   62   63   64   65   66   67