                                          Maha Metro in the process of setting up

                                           country’s fi rst 4-layer transportation on

                                                                Kamptee Road

           •  Country’s Largest          Maha Metro is in the process of setting up   task.
              Double Decker Girder       country’s first 4-layer transportation on Kamptee
              Coming Up in Reach-II      Road. The four layer transportation includes   Highlights of the Steel Structure:
           •  The 1,634 tonne Huge       the existing road and the railway track, above   •  The girder will be at a height of 24 metres
                                                                                from the ground.
                                         it. The flyover and the Metro Via-duct - both
              Structure Fabricated at    being constructed by Maha Metro - form the   •  The total weight of the girder is 1,634 tonnes.
              Butibori Industrial Estate  third and the fourth layer of the transportation   •  In all, 154 workers took part in the
                                         system. The via-duct is part of Reach-II,   preparation of its spare parts.
                                         which stretches from Sitabuldi Interchange to   •  A 78,000 capacity High Strength Friction
                                         Automotive Square. This is the second such   Grip (HSFG) bolt was used for erection.
                                         unique construction after Balanced Cantilever,
                                         which has been erected near Anand Talkies as   The proposed flyover and Metro Track share the
                                         part of Reach-IV alignment.          ‘Right of Way’, which effectively means that the
                                         The huge structure weighs 1,634 tonnes and   two structures have been constructed on the
                                         has been fabricated at Butibori Industrial Estate.   same pier, thus saving space and expenditure
                                         The monolith structure was first fabricated and   in the process. This was all the more essential
                                         then dismantled at Butibori and is being shifted   as the Kamptee Road, on which the structure
                                         to the work site by road. The robust condition   is being erected is one of the busiest roads of
                                         of the steel structure can be gauged from the   the city. The flyover starts at Automotive Square
                                         fact that two cranes of 250 tonne capacity   and ends at LIC Square. One completed, the
                                         were required while erecting it. Similarly, given   multi-layer transportation structure will not just
                                         the height at which the structure would be   add tot eh beauty and charm of the city, but
                                         erected at Gaddigodam, two cranes of 500   would also effectively reduce traffic congestion
                                         tonne capacity would be needed for the same   on the existing road.